Board of Trustees -3- November 22, 1988 Dormitory and Other Construction Projects- At the beginning of the construction phase, there were problems with SCI (the construction firm chosen) which did not appear to be organized to get its work started on time. More recently they have been working steadily, with a more workmanlike approach. While the Dormitory construction is now moving along fairly well, the President briefed the Board on the problems encountered at the beginning of the construction phase. These included a dispute over whether AUC owned the walls on the building site and a number of problems with those living next to the construction site. While it is still possible to complete the building as scheduled in May 1990, the problem...