Document: Pacific Southwest Water Plan "Printed Copy" Chapter VIII, August 26 ,1963 page 5Immediate-Action Program It is proposed that immediate authorization for the construction of urgently needed projects be included in legislation implementing the Pacific Southwest Water Plan. Only projects previously investigated and found to be economically justified and financially feasible, as noted before, are intended to be proposed. These include: a. Bridge Canyon Dam, reservoir, powerplant, transmission, and appurtenant facilities. It is intended that the dam be constructed so as to impound water at a normal water-surface elevation of 1,866 feet above mean sea level. b. Marble Canyon Dam, reservoir, powerplant, transmission, and appurt...