Document: Alternative Plan No. 3, 1-26-67, page 11-26-67 Alternative Plan No. 3 No Project Power Generation Federal Writeoff of a Portion of the Reimbursable Costs Proposal This alternative would provide for the construction of the Central Arizona Unit without any project power generation. Commercial power would be purchased for pumping. Without the provisions for project generation of low-cost pumping power, and with an M&I water rate of $51 per acre-foot to accomplish M&I repayment, the project would be unable to repay $322 million of its total estimated construction cost and $165 million of its operation and maintenance cost. In this alternative, a Federal writeoff of this $487 million balance would be proposed. Construc...