The construction of the Trenggalek District Health Office Building is a large-scale construction project. Large-scale projects often have performance issues. It is necessary to control costs and schedules for the project to go according to plan. Research using the Earned Value Method aims to find out the performance index, estimate the cost and time of completion of the work. They thus obtained corrections that must be made to the progress of the project. The results of the study in the 12th week were Budgeted Cost of Work Scheduled (BCWS) amounting to Rp1,946,626,471.64, Budgeted Cost of Work Performed (BCWP) amounted to Rp1,319,204,394.05, Actual Cost of Work Performed (ACWP) of Rp1,181,554,085.52. Performance costs benefit; Cost Varian (...
ABSTRACT During the construction period there is often an incompatibility schedule between the plann...
The construction of developing in Palembang is getting bigger and complicated both in the cost and t...
Perencanaan jadwal dan biaya pada proyek konstruksi disusun agar dalam pelaksanaan berjalan dengan l...
The construction of the Trenggalek District Health Office Building is a large-scale construction pro...
Construction projects have their own complexity, from physical and cost planning, time control and b...
In a construction project, there are several aspects that cause the project not to go according to p...
The construction of the Dongko Trenggalek District Building is one of the Trenggalek government's wo...
The main resources limited to the stage of implementing a construction project are cost, quality and...
Construction projects have their own complexity, from physical and cost planning, time control and b...
Planning and controlling costs and time is part of the overall construction project management. In a...
AbstrakPada sebuah proyek konstruksi sering terjadi keterlambatan penyelesaian kegiatan proyek, untu...
The East Java Province Inspectorate Building Construction Project Phase II has an important role in ...
Cost, quality, and time are mandatory targets of construction management; project work can be said t...
along with the development of the construction industry in Indonesia which is very advanced, the con...
cost and time planning and control are part of overall construction project management. The cost and...
ABSTRACT During the construction period there is often an incompatibility schedule between the plann...
The construction of developing in Palembang is getting bigger and complicated both in the cost and t...
Perencanaan jadwal dan biaya pada proyek konstruksi disusun agar dalam pelaksanaan berjalan dengan l...
The construction of the Trenggalek District Health Office Building is a large-scale construction pro...
Construction projects have their own complexity, from physical and cost planning, time control and b...
In a construction project, there are several aspects that cause the project not to go according to p...
The construction of the Dongko Trenggalek District Building is one of the Trenggalek government's wo...
The main resources limited to the stage of implementing a construction project are cost, quality and...
Construction projects have their own complexity, from physical and cost planning, time control and b...
Planning and controlling costs and time is part of the overall construction project management. In a...
AbstrakPada sebuah proyek konstruksi sering terjadi keterlambatan penyelesaian kegiatan proyek, untu...
The East Java Province Inspectorate Building Construction Project Phase II has an important role in ...
Cost, quality, and time are mandatory targets of construction management; project work can be said t...
along with the development of the construction industry in Indonesia which is very advanced, the con...
cost and time planning and control are part of overall construction project management. The cost and...
ABSTRACT During the construction period there is often an incompatibility schedule between the plann...
The construction of developing in Palembang is getting bigger and complicated both in the cost and t...
Perencanaan jadwal dan biaya pada proyek konstruksi disusun agar dalam pelaksanaan berjalan dengan l...