This 2-page fact sheet provides information about a new approach that would increase accuracy in determining the optimal time to saw freshly placed concrete
According to ASTM 403C, initial setting time of concrete is measured based on penetration resistance...
With knowledge of the time to initial set, contractors will be able plan measures to finish, texture...
US Transportation Collection2018PDFTech ReportCrovetti, James A.Kevern, John T.Marquette University....
At present, there is little fundamental guidance available to assist contractors in choosing when to...
Joints are placed in Portland cement concrete pavements (PCCP) to control random cracking. These joi...
PDFTech ReportIHRB Project TR-675InTrans Project 14-498Sawed jointsSawingSetting (Concrete)Ultrasoni...
Early-age cracking and spalling in concrete pavements reduces slab capacity, joint load transfer, ri...
Concrete sawing operations are performed at pre-determined locations within the first 24 hours to pr...
Early entry sawing applies sawing earlier and more shallowly than conventional sawing and is believe...
Early entry sawing applies sawing earlier and more shallowly than conventional sawing and is believe...
Early-entry sawing is an attractive operation to expedite the construction of jointed concrete pavem...
2007PDFTech Reporthttps://www.fhwa.dot.gov/pavement/concrete/pubs/07031/07031.pdfhttps://www.fhwa.do...
Transferred from EDL on 5/14/2008PDFTech ReportUnited States. Joint Program Office for Intelligent T...
Fast track concrete technology has been used over the past two decades for overnight highway repairs...
Determining the opening time for a concrete pavement is a critical decision. Longer construction tim...
According to ASTM 403C, initial setting time of concrete is measured based on penetration resistance...
With knowledge of the time to initial set, contractors will be able plan measures to finish, texture...
US Transportation Collection2018PDFTech ReportCrovetti, James A.Kevern, John T.Marquette University....
At present, there is little fundamental guidance available to assist contractors in choosing when to...
Joints are placed in Portland cement concrete pavements (PCCP) to control random cracking. These joi...
PDFTech ReportIHRB Project TR-675InTrans Project 14-498Sawed jointsSawingSetting (Concrete)Ultrasoni...
Early-age cracking and spalling in concrete pavements reduces slab capacity, joint load transfer, ri...
Concrete sawing operations are performed at pre-determined locations within the first 24 hours to pr...
Early entry sawing applies sawing earlier and more shallowly than conventional sawing and is believe...
Early entry sawing applies sawing earlier and more shallowly than conventional sawing and is believe...
Early-entry sawing is an attractive operation to expedite the construction of jointed concrete pavem...
2007PDFTech Reporthttps://www.fhwa.dot.gov/pavement/concrete/pubs/07031/07031.pdfhttps://www.fhwa.do...
Transferred from EDL on 5/14/2008PDFTech ReportUnited States. Joint Program Office for Intelligent T...
Fast track concrete technology has been used over the past two decades for overnight highway repairs...
Determining the opening time for a concrete pavement is a critical decision. Longer construction tim...
According to ASTM 403C, initial setting time of concrete is measured based on penetration resistance...
With knowledge of the time to initial set, contractors will be able plan measures to finish, texture...
US Transportation Collection2018PDFTech ReportCrovetti, James A.Kevern, John T.Marquette University....