AbstractThis paper deals with problems of computing possible values of latest starting times and determining types of criticality for all activities in a network with interval or fuzzy activity durations. Although the problem of computing the latest starting times has been solved, a novel polynomial algorithm which is easy to understand and improves complexity is proposed.In networks with interval activity durations, instead of being critical or not, three sets of critical activities exist: an activity will be either necessarily noncritical, or necessarily critical, or possibly critical. Results of determining bounds of latest starting times are used to develop lemmas that establish the possible criticality of an activity in special cases i...
A project network consists of various activities. To determine the length of project time and the am...
Probabilistic critical path method PERT assumes beta distribution as probability distribution of tas...
In this paper, fuzzy critical path analysis of a project network is carried out. Metric distance ran...
ksInternational audienceThis paper deals with fuzzy activity networks, where fuzzy intervals model u...
BBInternational audienceThe notion of the necessary criticality (both with respect to path and to ac...
DFargFort003International audienceIn project management, three quantities are often used by project ...
Dedicated to the memory of Professor Stefan Chanas - The extended abstract version of this paper has...
International audienceIn project or production management, an activity network is classically define...
Abstract. A review of the results obtained in the area of fuzzy network analysis is presented. The m...
AbstractTriangular fuzzy numbers are used to represent project activities whose duration times are u...
In this paper, we analyze the project scheduling problem using fuzzy theory. The crisp activity dura...
This paper reconsiders the PERT scheduling problem when information about task dura-tion is incomple...
In this paper, we propose a new approach to Fuzzy network crashing in a project network whose activi...
International audienceGiven an activity-on-node network where every activity has an uncertain durati...
International audienceThis paper deals with the fuzzy project scheduling approach, where fuzzy inter...
A project network consists of various activities. To determine the length of project time and the am...
Probabilistic critical path method PERT assumes beta distribution as probability distribution of tas...
In this paper, fuzzy critical path analysis of a project network is carried out. Metric distance ran...
ksInternational audienceThis paper deals with fuzzy activity networks, where fuzzy intervals model u...
BBInternational audienceThe notion of the necessary criticality (both with respect to path and to ac...
DFargFort003International audienceIn project management, three quantities are often used by project ...
Dedicated to the memory of Professor Stefan Chanas - The extended abstract version of this paper has...
International audienceIn project or production management, an activity network is classically define...
Abstract. A review of the results obtained in the area of fuzzy network analysis is presented. The m...
AbstractTriangular fuzzy numbers are used to represent project activities whose duration times are u...
In this paper, we analyze the project scheduling problem using fuzzy theory. The crisp activity dura...
This paper reconsiders the PERT scheduling problem when information about task dura-tion is incomple...
In this paper, we propose a new approach to Fuzzy network crashing in a project network whose activi...
International audienceGiven an activity-on-node network where every activity has an uncertain durati...
International audienceThis paper deals with the fuzzy project scheduling approach, where fuzzy inter...
A project network consists of various activities. To determine the length of project time and the am...
Probabilistic critical path method PERT assumes beta distribution as probability distribution of tas...
In this paper, fuzzy critical path analysis of a project network is carried out. Metric distance ran...