AbstractDuring all planning stages of offshore projects, the assessment of the effects of adverse weather is essential. In order to address this problem, the WaTSS (Weather Time Series Scheduling) method and its application will be presented. The defined project schedule and the environmental data in form of weather time series are the input data.Three different case studies were carried out using one project schedule and different input time series. Within the first case, differences in the project progress due to minor differences in model and measurement data are displayed. In the second case, the effects of variations or uncertainty in the input time series are studied. Within the third case, the method is applied for a number of spatia...
This paper outlines proposed testing criteria for wind speed time series (WSTS) models. The objectiv...
Offshore wind farm maintenance operations are complex and dangerous, and as such are subject to stri...
This is the published version of the article. Available from Elsevier via the DOI in this record.The...
The significant lead times and costs associated with materials and equipment in combination with int...
Executed outdoors in high-wind areas, adverse weather conditions represent a significant risk to ons...
PROJECT ASSESSMENT Delays caused by adverse weather are a major problem during offshore wind farm in...
Wind farm installation and particularly offshore wind farm installation is highly complex due to hig...
For the planning stage in any wind farm development, there are many concepts and locations to be ana...
Analysis of the expected downtime in complex offshore operations is performed with metocean analysis...
The impact of (adverse) weather is a common cause of delays, legal claims and economic losses in con...
Marine operations play a pivotal role throughout all phases of a wind farm's life cycle. In particul...
The purpose of this master thesis is to examine the weather windows and the associated downtimes for...
This paper focuses on the scheduling problem in the offshore wind farm installation process, which i...
The focus in this research was the conversion of a traditional activity-based construction schedule ...
Wind power is highly dependent on wind speed and operations offshore are affected by wave height; th...
This paper outlines proposed testing criteria for wind speed time series (WSTS) models. The objectiv...
Offshore wind farm maintenance operations are complex and dangerous, and as such are subject to stri...
This is the published version of the article. Available from Elsevier via the DOI in this record.The...
The significant lead times and costs associated with materials and equipment in combination with int...
Executed outdoors in high-wind areas, adverse weather conditions represent a significant risk to ons...
PROJECT ASSESSMENT Delays caused by adverse weather are a major problem during offshore wind farm in...
Wind farm installation and particularly offshore wind farm installation is highly complex due to hig...
For the planning stage in any wind farm development, there are many concepts and locations to be ana...
Analysis of the expected downtime in complex offshore operations is performed with metocean analysis...
The impact of (adverse) weather is a common cause of delays, legal claims and economic losses in con...
Marine operations play a pivotal role throughout all phases of a wind farm's life cycle. In particul...
The purpose of this master thesis is to examine the weather windows and the associated downtimes for...
This paper focuses on the scheduling problem in the offshore wind farm installation process, which i...
The focus in this research was the conversion of a traditional activity-based construction schedule ...
Wind power is highly dependent on wind speed and operations offshore are affected by wave height; th...
This paper outlines proposed testing criteria for wind speed time series (WSTS) models. The objectiv...
Offshore wind farm maintenance operations are complex and dangerous, and as such are subject to stri...
This is the published version of the article. Available from Elsevier via the DOI in this record.The...