A failure assessment method of stay cables containing fractured wires is presented through an example of an existing bridge. The wires constituting the stay cables of the bridge contained many initial defects that were formed during the rolling process of these wires. Despite moderate loading, fatigue cracks started to grow from these defects, increasing their size, and finally resulting in fracture of the remaining ligament of the wires. A probabilistic model is put forward for assessing the resistance of the stay cable based on a fracture mechanics model of the individual wires. A Bayesian update method is presented for estimating the distribution of initial defects based on the inspection of fractured wires. The calculated reliability of...
The safe life method for the fatigue life prediction of steel bridges has for several cases been sho...
A damage tolerance method for fatigue assessment opens the possibility of combining theoretical asse...
The Central Bridge over the Ohio River between Newport, Kentucky, and Cincinnati, Ohio, was complete...
A failure assessment method of stay cables containing fractured wires is presented through an exampl...
A failure assessment method of stay cables containing fractured wires is presented through an exampl...
In structures submitted to repeated variable loads, initiation and growth of cracks in the material ...
Bridge inspections reveal that severe corrosion and fatigue are the main failure mechanisms of bridg...
Cables/hangers are important load-bearing components of suspension, cable-stayed, and through-arch b...
Fatigue fracture of bridge stay-cables is usually a multiscale process as the crack grows from micro...
Civil infrastructures are in many countries ageing and maintenance is necessary in order to secure m...
PDFTech ReportFHWA-OR-RD-00-08SPR 380Fatigue crackingBridge decksFinite element methodSteel bridgesP...
textStructural reliability techniques can be employed to evaluate the fatigue performance of fractur...
According to a study conducted by the ASCE Committee on Fatigue and Fracture Reliability, 80–90% of ...
Long-span cable-stayed bridges have gained increasing popularity due to their appealing aesthetics, ...
This paper presents results of a failure analysis study to characterize the damage phenomenon that o...
The safe life method for the fatigue life prediction of steel bridges has for several cases been sho...
A damage tolerance method for fatigue assessment opens the possibility of combining theoretical asse...
The Central Bridge over the Ohio River between Newport, Kentucky, and Cincinnati, Ohio, was complete...
A failure assessment method of stay cables containing fractured wires is presented through an exampl...
A failure assessment method of stay cables containing fractured wires is presented through an exampl...
In structures submitted to repeated variable loads, initiation and growth of cracks in the material ...
Bridge inspections reveal that severe corrosion and fatigue are the main failure mechanisms of bridg...
Cables/hangers are important load-bearing components of suspension, cable-stayed, and through-arch b...
Fatigue fracture of bridge stay-cables is usually a multiscale process as the crack grows from micro...
Civil infrastructures are in many countries ageing and maintenance is necessary in order to secure m...
PDFTech ReportFHWA-OR-RD-00-08SPR 380Fatigue crackingBridge decksFinite element methodSteel bridgesP...
textStructural reliability techniques can be employed to evaluate the fatigue performance of fractur...
According to a study conducted by the ASCE Committee on Fatigue and Fracture Reliability, 80–90% of ...
Long-span cable-stayed bridges have gained increasing popularity due to their appealing aesthetics, ...
This paper presents results of a failure analysis study to characterize the damage phenomenon that o...
The safe life method for the fatigue life prediction of steel bridges has for several cases been sho...
A damage tolerance method for fatigue assessment opens the possibility of combining theoretical asse...
The Central Bridge over the Ohio River between Newport, Kentucky, and Cincinnati, Ohio, was complete...