The program is organized into three developmental periods. In Phase 1 the team will develop and demonstrate a proof-of-concept prototype design and develop a manufacturing plan to substantiate potential producibility at a target cost level of $800/kW factory manufacturing cost. Phase 2 will further develop the design and reduce the manufacturing cost to a level of $600 kW. Depending on an assessment of the maturity of the technology at the end of Phase 1, Phase 2 may be structured and supplemented to provide a limited production capability. Finally, in Phase 3, a full Value Package Introduction (VPI) Program will be integrated into the SECA program to develop a mass-producible design at a factory cost of $400/kW with full cross-functional s...