The purpose of this document is to establish quantitative expressions of proposed costs and schedule to serve as a basis for measurement of program performance. It identifies the components of the Program Cost and Schedule Baseline (PCSB) that will be subject to change control by the Executive (Level 0) and Program (Level 1) Change Control Boards (CCBS) and establishes their baseline values. This document also details PCSB reporting, monitoring, and corrective action requirements. The Program technical baseline contained in the Waste Management System Description (WMSD), the Waste Management System Requirements (WMSR), and the Physical System Requirements documents provide the technical basis for the PCSB. Changes to the PCSB will be approv...