This paper is part of the IMFG Perspectives Papers series. For a full list of papers, please visit http://bit.ly/2ylAa2D.Cost overruns and schedule delays on infrastructure megaprojects are a common news story in the media, in Canada and around the world. The outcomes include government budget deficits and a loss of public confidence that the government can meet its commitments. The three main explanations for cost overruns and delays are technical challenges, over-optimism, and strategic misrepresentations. International best practices suggest at least five remedies for these problems. First, improved performance monitoring, reporting, and information sharing is a feasible option in a world in which data management is becoming increasin...
© 2016 Elsevier LtdUnderstanding the cause of cost overruns in transportation infrastructure project...
In the public arena, we often hear about projects that have suffered massive cost overruns. Often th...
Infrastructure projects regularly experience cost and schedule overruns. Research led by Flyvbjerg h...
PurposeThe purpose of this paper is to explore the impact that cost overruns and time delays exert o...
In recent years, there has been a sharp growth in both the magnitude and frequency of major infrastr...
Over the past fifteen years, Australian governments have spent $28 billion more on transport infrast...
Many infrastructure projects have cost overruns and there has been a lot of research both on why the...
Purpose of this paper The construction industry is distinct and different from other industries due ...
AbstractInfrastructure projects regularly experience cost and schedule overruns. Research led by Fly...
Media reports abound on instances of prolonged delays and excessive cost overruns in infrastructure ...
Cost and schedule overruns are endemic features of transport infrastructure projects. Despite the co...
The amount of risk in mega infrastructure projects (MIPs) has undoubtedly contributed to the rising ...
Abstract For decades, the construction industry has been characterized by costs exceeding budgetary ...
For decades, the construction industry has been characterized by costs exceeding budgetary limits an...
Delays and cost overruns in Public Sector investments can raise the capital-output ratio in the sect...
© 2016 Elsevier LtdUnderstanding the cause of cost overruns in transportation infrastructure project...
In the public arena, we often hear about projects that have suffered massive cost overruns. Often th...
Infrastructure projects regularly experience cost and schedule overruns. Research led by Flyvbjerg h...
PurposeThe purpose of this paper is to explore the impact that cost overruns and time delays exert o...
In recent years, there has been a sharp growth in both the magnitude and frequency of major infrastr...
Over the past fifteen years, Australian governments have spent $28 billion more on transport infrast...
Many infrastructure projects have cost overruns and there has been a lot of research both on why the...
Purpose of this paper The construction industry is distinct and different from other industries due ...
AbstractInfrastructure projects regularly experience cost and schedule overruns. Research led by Fly...
Media reports abound on instances of prolonged delays and excessive cost overruns in infrastructure ...
Cost and schedule overruns are endemic features of transport infrastructure projects. Despite the co...
The amount of risk in mega infrastructure projects (MIPs) has undoubtedly contributed to the rising ...
Abstract For decades, the construction industry has been characterized by costs exceeding budgetary ...
For decades, the construction industry has been characterized by costs exceeding budgetary limits an...
Delays and cost overruns in Public Sector investments can raise the capital-output ratio in the sect...
© 2016 Elsevier LtdUnderstanding the cause of cost overruns in transportation infrastructure project...
In the public arena, we often hear about projects that have suffered massive cost overruns. Often th...
Infrastructure projects regularly experience cost and schedule overruns. Research led by Flyvbjerg h...