In a project environment, a manufacturer is confronted with two types of demand: regular demand from many small orders and very irregular, lumpy demand from infrequent, large orders. Manufacturers who build to stock must carry large safety stocks to meet the lumpy demand. As part of the project engineering process, however, project engineers and implementers (e.g. installers) typically have developed information about material requirements well in advance of placement of orders. We analyze the inventory reduction that could be achieved if the installer were to communicate advance demand information (ADI) to the manufacturer. We look at it in particular when the bid is placed. We focus on the following characteristics of available ADI in pro...