The performance of a container terminal heavily relies on how efficiently the quayside resources, which are mainly berth and quay cranes, are used. The quayside related planning problems face uncertainty in various parameters, and this makes the efficient planning of these operations even more complicated. This study aims at developing a recoverable robust optimization approach for the weekly berth and quay crane planning problem. In order to build systematic recoverable robustness, a proactive baseline schedule with reactive recovery costs has been suggested. The uncertainty of vessel arrivals and the fluctuation in the container handling rate of quay cranes are considered. The baseline schedule includes berthing positions, times and quay ...
The scheduling of quay cranes (QCs) to minimize the handling time of a berthed vessel is one of the ...
Traditionally, terminal operators create an initial berthing plan before the arrival of incoming ves...
The baseline plan of terminals will be impacted to a certain extent after being affected by uncertai...
This study discusses the development of tactical-level integrated planning at seaport container ter...
In a container terminal, the quay cranes (QCs) are the main equipment involved in the core activitie...
Port terminals play a critical role in the context of world trade since they are the main nodes resp...
Maximum utilization of resources is the key aspect for reducing the turnaround time of vessel calls ...
Copyright © 2013 ISSR Journals. This is an open access article distributed under the Creative Common...
We consider a container terminal operator who faces the problem ofconstructing a cyclic berth plan. ...
We consider an integrated berth allocation and quay crane assignment and scheduling problem where th...
In order to solve the large-scale integral dynamic scheduling of continuous berths and quay cranes p...
This paper constructs a berth-quay crane capacity planning model with the lowest average daily cost ...
In this report, a heuristic quay crane scheduling algorithm is designed to tackle the problem of det...
Abstract The main challenge for a container terminal is to maximize its throughput using limited res...
This paper proposes a simulation optimization based solution approach for the integrated Berth Alloc...
The scheduling of quay cranes (QCs) to minimize the handling time of a berthed vessel is one of the ...
Traditionally, terminal operators create an initial berthing plan before the arrival of incoming ves...
The baseline plan of terminals will be impacted to a certain extent after being affected by uncertai...
This study discusses the development of tactical-level integrated planning at seaport container ter...
In a container terminal, the quay cranes (QCs) are the main equipment involved in the core activitie...
Port terminals play a critical role in the context of world trade since they are the main nodes resp...
Maximum utilization of resources is the key aspect for reducing the turnaround time of vessel calls ...
Copyright © 2013 ISSR Journals. This is an open access article distributed under the Creative Common...
We consider a container terminal operator who faces the problem ofconstructing a cyclic berth plan. ...
We consider an integrated berth allocation and quay crane assignment and scheduling problem where th...
In order to solve the large-scale integral dynamic scheduling of continuous berths and quay cranes p...
This paper constructs a berth-quay crane capacity planning model with the lowest average daily cost ...
In this report, a heuristic quay crane scheduling algorithm is designed to tackle the problem of det...
Abstract The main challenge for a container terminal is to maximize its throughput using limited res...
This paper proposes a simulation optimization based solution approach for the integrated Berth Alloc...
The scheduling of quay cranes (QCs) to minimize the handling time of a berthed vessel is one of the ...
Traditionally, terminal operators create an initial berthing plan before the arrival of incoming ves...
The baseline plan of terminals will be impacted to a certain extent after being affected by uncertai...