Dedicated to the memory of Professor Stefan Chanas - The extended abstract version of this paper has appeared in Proceedings of 11th International Conference on Principles and Practice of Constraint Programming (CP2005) ("Interval Analysis in Scheduling", Fortin et al. 2005)International audienceThis paper reconsiders the Project Evaluation and Review Technique (PERT) scheduling problem when information about task duration is incomplete. We model uncertainty on task durations by intervals. With this problem formulation, our goal is to assert possible and necessary criticality of the different tasks and to compute their possible earliest starting dates, latest starting dates, and floats. This paper combines various results and provides a com...
We study the problem of scheduling project activities with precedence constraints and unlimited reso...
this paper. The project starts at the initial node and ends at the terminal node. A path is a set of...
Since its invention in 1958, Program Evaluation and Review Technique (PERT) has been widely used dur...
Dedicated to the memory of Professor Stefan Chanas - The extended abstract version of this paper has...
This paper reconsiders the PERT scheduling problem when information about task dura-tion is incomple...
International audienceIn project or production management, an activity network is classically define...
DFargFort003International audienceIn project management, three quantities are often used by project ...
AbstractThis paper deals with problems of computing possible values of latest starting times and det...
International audienceGiven an activity-on-node network where every activity has an uncertain durati...
The critical path method (CPM), project evaluation and review technique (PERT), and stochastic PERT,...
The purpose of this paper is to propose models for project scheduling when there is considerable un...
International audienceThis paper considers the following basic problem in scheduling under uncertain...
PERT (Program Evaluation and Review Technique), developed in the 1950’s, represented the ...
We study the problem of scheduling project activities with precedence constraints and unlimited reso...
this paper. The project starts at the initial node and ends at the terminal node. A path is a set of...
Since its invention in 1958, Program Evaluation and Review Technique (PERT) has been widely used dur...
Dedicated to the memory of Professor Stefan Chanas - The extended abstract version of this paper has...
This paper reconsiders the PERT scheduling problem when information about task dura-tion is incomple...
International audienceIn project or production management, an activity network is classically define...
DFargFort003International audienceIn project management, three quantities are often used by project ...
AbstractThis paper deals with problems of computing possible values of latest starting times and det...
International audienceGiven an activity-on-node network where every activity has an uncertain durati...
The critical path method (CPM), project evaluation and review technique (PERT), and stochastic PERT,...
The purpose of this paper is to propose models for project scheduling when there is considerable un...
International audienceThis paper considers the following basic problem in scheduling under uncertain...
PERT (Program Evaluation and Review Technique), developed in the 1950’s, represented the ...
We study the problem of scheduling project activities with precedence constraints and unlimited reso...
this paper. The project starts at the initial node and ends at the terminal node. A path is a set of...
Since its invention in 1958, Program Evaluation and Review Technique (PERT) has been widely used dur...