The Storage Tank Project is a national vital object that supports the operational reliability program of the Fuel Oil distribution. But there was a delay in the implementation of work by 31.35%. This research purpose to identify the factors and indicators that cause delays in the storage tank construction project. This research method uses Fault Tree Analysis. Factors and indicators are FTA Event inputs which are then illustrated by FTA diagrams. FTA using Boolean algebra formulation results in a probability value for each Event.Objek research is in the construction Storage tanks in Surabaya. Work items in the research are Foundation work with a weight of 26.50% and Construction Work with a weight of 36.94%. From the results of this researc...
The construction project will achieve success if the parties were able complete the construction pro...
This research is conducted to determine the delay factors in time and cost in the advanced construct...
This research aims to: find out the causative factors of delay in project completion and the rank ba...
The Storage Tank Project is a national vital object that supports the operational reliability progra...
Proyek Pembangunan Storage Tank Perusahaan Oil dan Gas Milik Negara di area Jawa Timur merupakan pro...
Purpose: In construction projects, delays are disruptive and expensive. Therefore, the reason for th...
AbstractIn a project, timeliness in doing any job should be emphasized in addition to the quality of...
ii Delays in construction projects are inevitable; as a result claims and disputes arise among diffe...
PLN Unit Induk Pembangunan Kalimantan Bagian Timur (PLN UIP Kalbagtim) is a company that is responsi...
Dengan kemajuan zaman seperti saat ini banyak wilayah perkotaan mengalami perkembangan sangat pesat ...
Reparasi kapal merupakan sebuah proyek yang singkat dalam prosesnya sehingga waktu merupakan elemen ...
Abstract.This research focuses on finding the root problem of the construction delay that happened i...
Delays in construction projects are both disruptive and expensive. Thus, potential causes of schedul...
Maintenance activities on power plant projects, which are located in remote areas, are prone to risk...
Dalam proses distribusi tenaga listrik, terdapat banyak aset yang digunakan hingga listrik dapat ter...
The construction project will achieve success if the parties were able complete the construction pro...
This research is conducted to determine the delay factors in time and cost in the advanced construct...
This research aims to: find out the causative factors of delay in project completion and the rank ba...
The Storage Tank Project is a national vital object that supports the operational reliability progra...
Proyek Pembangunan Storage Tank Perusahaan Oil dan Gas Milik Negara di area Jawa Timur merupakan pro...
Purpose: In construction projects, delays are disruptive and expensive. Therefore, the reason for th...
AbstractIn a project, timeliness in doing any job should be emphasized in addition to the quality of...
ii Delays in construction projects are inevitable; as a result claims and disputes arise among diffe...
PLN Unit Induk Pembangunan Kalimantan Bagian Timur (PLN UIP Kalbagtim) is a company that is responsi...
Dengan kemajuan zaman seperti saat ini banyak wilayah perkotaan mengalami perkembangan sangat pesat ...
Reparasi kapal merupakan sebuah proyek yang singkat dalam prosesnya sehingga waktu merupakan elemen ...
Abstract.This research focuses on finding the root problem of the construction delay that happened i...
Delays in construction projects are both disruptive and expensive. Thus, potential causes of schedul...
Maintenance activities on power plant projects, which are located in remote areas, are prone to risk...
Dalam proses distribusi tenaga listrik, terdapat banyak aset yang digunakan hingga listrik dapat ter...
The construction project will achieve success if the parties were able complete the construction pro...
This research is conducted to determine the delay factors in time and cost in the advanced construct...
This research aims to: find out the causative factors of delay in project completion and the rank ba...