The actual completion time of construction projects is rarely in accordance with initial plans. This is due to unforeseen events that affect the project execution. In the paper, the authors propose a method of improving the construction schedule reliability. The method is based on the idea of buffers allocation, whose proper sizing helps to reduce negative effects of random conditions on the progress and efficiency of project activities. The authors adopt a proactive approach to the construction of robust schedules to cope with multiple disruptions during project execution, applicable to two processes starting policies (as soon as possible or no sooner than on a predefined date). The proposed method, based on simulation technique and mathem...
Several criteria must be considered while preparing the schedule of a construction project. The comp...
The paper present the concept of stability assessing the of solutions which are construction schedul...
Several projects under random disturbances have to be realized in a project office within the planni...
Referat dotyczy zagadnienia uodporniania planowanych terminów rozpoczynania robót, na zakłócenia pow...
The literature offers numerous proposals for calculating the project buffer, located at the end of t...
Potential applications of the CCS/BM method in the scheduling of continuous LSM (Linear Scheduling M...
AbstractWe propose a new concept of a robust project schedule. The concept is based on the applicati...
Solution robust project scheduling is a growing research field aiming at constructing proactive sche...
Duration of construction projects can be reduced by harmonizing construction processes: adjusting pr...
Na czas realizacji procesów budowlanych wpływa wiele czynników, których częstość i siła oddziaływani...
The vast majority of research efforts in project scheduling concentrates on developing procedures to...
The methodology of development of building project schedules, proposed in the article, is based on a...
Solution-robust project scheduling is a growing research field aiming at constructing proactive sche...
The rapidly changing marketplace together with the increasing complexity of contemporary projects ma...
The paper present the concept of stability assessing the of solutions which are construction schedul...
Several criteria must be considered while preparing the schedule of a construction project. The comp...
The paper present the concept of stability assessing the of solutions which are construction schedul...
Several projects under random disturbances have to be realized in a project office within the planni...
Referat dotyczy zagadnienia uodporniania planowanych terminów rozpoczynania robót, na zakłócenia pow...
The literature offers numerous proposals for calculating the project buffer, located at the end of t...
Potential applications of the CCS/BM method in the scheduling of continuous LSM (Linear Scheduling M...
AbstractWe propose a new concept of a robust project schedule. The concept is based on the applicati...
Solution robust project scheduling is a growing research field aiming at constructing proactive sche...
Duration of construction projects can be reduced by harmonizing construction processes: adjusting pr...
Na czas realizacji procesów budowlanych wpływa wiele czynników, których częstość i siła oddziaływani...
The vast majority of research efforts in project scheduling concentrates on developing procedures to...
The methodology of development of building project schedules, proposed in the article, is based on a...
Solution-robust project scheduling is a growing research field aiming at constructing proactive sche...
The rapidly changing marketplace together with the increasing complexity of contemporary projects ma...
The paper present the concept of stability assessing the of solutions which are construction schedul...
Several criteria must be considered while preparing the schedule of a construction project. The comp...
The paper present the concept of stability assessing the of solutions which are construction schedul...
Several projects under random disturbances have to be realized in a project office within the planni...