This paper discusses the process of original soil stabilization in Trans Sumatra Bakauheni-Terbanggi Besar Toll Road Project Package 2 Sidomulyo-Kotabaru. The soil replacement process was conducted at approximately 24 kilometres along the toll’s main road. The original soil bearing capacity analysis stage was by performing a Dynamic Cone Penetrometer (DCP) and Sondir test to analyze the deep of hard soil. A soil replacement was carried out to replace the original soil with soil that has appropriate specification. the piling up process was conducted in stages, which has Sandstone in such of the layer. The research done about the landfill sample was retaken and collected at 68 points. The stockpile soil samples collection was then followed by...