In large and complex project schedule networks, existing algorithms to determine the critical path are considerably slow. Therefore, an algorithm with a faster convergence is needed to improve the efficiency of the critical path computation. The ant colony algorithm was first applied to the travelling salesman problem to determine the shortest path. However, many problems require the longest path in practice; the critical path in the scheduling problem is the longest path in the scheduling network. In this study, an improved ant colony algorithm to determine the critical path by setting the path distance and time as negative, while the transition probability remains unchanged, is proposed. The case of a coal power plant engineering, procure...