As any other accelerator, the LHC has to undertake periods of stop for maintenance. Five technical stops have been performed during the 2011 run and sometimes a quite long recovery time was experienced. An analysis of the reasons is presented paying particular attention to the interventions carried out during the stop. Following this analysis, an outlook on the future that aims to increase the LHC availability and to diminish the downtime is also considered. Further consideration is put on the possibility to perform maintenance only once the machine undergoes a problem, instead of during planned stops
The first shutdown of the LHC machine started on the 17th of November 2008. In addition to typical s...
Since 2010, CERN has entered a mode of continuous operation of the LHC and its injectors, which impl...
The potential limitations for future running of the LHC RF systems are presented. In particular the ...
The LHC and its Injectors are submitted to an overall lifecycle of three to four years of physics de...
During the winter 2016/2017 the LHC will undertake a period of maintenance, the so-called Extended Y...
The few weeks of LHC operation in 2009 was a resounding success with extremely fast progress in the ...
This document summarises the LHC machine availability for the period of Technical Stop 1 (TS1) to Te...
The operational efficiency of the LHC is analyzed by looking at the downtime statistics over the 201...
At the end of 2012, the Large Hadron Collider will enter its first programmed long stop (LS1). The p...
This document summarises the LHC machine availability for the period of Technical Stop 1 (TS1) to Te...
This document summarises the LHC machine availability for the period of Technical Stop 1 (TS1) to Te...
This document summarises the LHC machine availability for the period of Restart to Technical Stop 1 ...
The shutdown originally planned for 2011-13 is the first opportunity since physics operation started...
During the LHC operation in 2010 and 2011, the cryogenic system has achieved an availability level f...
This document summarises the LHC machine availability for the period of Restart to Technical Stop 1 ...
The first shutdown of the LHC machine started on the 17th of November 2008. In addition to typical s...
Since 2010, CERN has entered a mode of continuous operation of the LHC and its injectors, which impl...
The potential limitations for future running of the LHC RF systems are presented. In particular the ...
The LHC and its Injectors are submitted to an overall lifecycle of three to four years of physics de...
During the winter 2016/2017 the LHC will undertake a period of maintenance, the so-called Extended Y...
The few weeks of LHC operation in 2009 was a resounding success with extremely fast progress in the ...
This document summarises the LHC machine availability for the period of Technical Stop 1 (TS1) to Te...
The operational efficiency of the LHC is analyzed by looking at the downtime statistics over the 201...
At the end of 2012, the Large Hadron Collider will enter its first programmed long stop (LS1). The p...
This document summarises the LHC machine availability for the period of Technical Stop 1 (TS1) to Te...
This document summarises the LHC machine availability for the period of Technical Stop 1 (TS1) to Te...
This document summarises the LHC machine availability for the period of Restart to Technical Stop 1 ...
The shutdown originally planned for 2011-13 is the first opportunity since physics operation started...
During the LHC operation in 2010 and 2011, the cryogenic system has achieved an availability level f...
This document summarises the LHC machine availability for the period of Restart to Technical Stop 1 ...
The first shutdown of the LHC machine started on the 17th of November 2008. In addition to typical s...
Since 2010, CERN has entered a mode of continuous operation of the LHC and its injectors, which impl...
The potential limitations for future running of the LHC RF systems are presented. In particular the ...