After the initial plans in 2007 to run the LHC at 7 TeV, a number of unexpected events, and the extended knowledge of the machine that came after them, have convinced us to gradually reduce the beam energy to the current 3.5 TeV. As a consequence of this, some circuits have been commissioned to different energy levels. Some systems, as the quench protection system, are working at a reduced level of accuracy based on less demanding conditions. Nonconformities that were unacceptable for higher energy have no consequences at the current energy and are thus accepted. In this talk, we will review the current status of commissioning of all the circuits and estimate the time and effort necessary to make all circuits operational at higher energies....