In this work, we consider RCPSP/max with durational uncertainty. We focus on computing robust Partial Order Schedules (or, in short POS) which can be executed with risk controlled feasibility and optimality, i.e., there is stochastic posteriori quality guarantee that the derived POS can be executed with all constraints honored and completion before robust makespan. To address this problem, we propose BACCHUS: a solution method on Benders Accelerated Cut Creation for Handling Uncertainty in Scheduling. In our proposed approach, we first give an MILP formulation for the deterministic RCPSP/max and partition the model into POS generation process and start time schedule determination. Then we develop Benders algorithm and propose cut generation...
AbstractLogistics project scheduling problem in indeterminate environment is gaining more and more a...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...
Robustness is essential for schedules if they are being executed under uncertain conditions. In this...
Resource Constrained Project Scheduling Problems with minimum and maximum time lags (RCPSP/max) prov...
Resource Constrained Project Scheduling Problems with minimum and maximum time lags (RCPSP/max) have...
This paper is about characterizing the expected makespan of a Partial Order Schedule (POS) under dur...
International audienceIn this chapter, we examine the RCPSP for the case when there is considerable ...
© 2017 Elsevier Ltd In this paper, we consider Resource Constrained Project Scheduling Problems (RCP...
The resource-constrained project scheduling problem (RCPSP) with stochastic activity durations invol...
We consider the Resource-Constrained Project Scheduling Problem with minimal and maximal time lags u...
Uncertainty in activity durations is a key characteristic of many real world scheduling problems in ...
In real-world project scheduling applications, activity durations are often uncertain. Proactive sch...
Abstract. In the context of Scheduling under uncertainty, Partial Order Schedules (POS) provide a co...
In this paper, we propose an extended local search frame-work to solve combinatorial optimization pr...
The purpose of this paper is to propose models for project scheduling when there is considerable unc...
AbstractLogistics project scheduling problem in indeterminate environment is gaining more and more a...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...
Robustness is essential for schedules if they are being executed under uncertain conditions. In this...
Resource Constrained Project Scheduling Problems with minimum and maximum time lags (RCPSP/max) prov...
Resource Constrained Project Scheduling Problems with minimum and maximum time lags (RCPSP/max) have...
This paper is about characterizing the expected makespan of a Partial Order Schedule (POS) under dur...
International audienceIn this chapter, we examine the RCPSP for the case when there is considerable ...
© 2017 Elsevier Ltd In this paper, we consider Resource Constrained Project Scheduling Problems (RCP...
The resource-constrained project scheduling problem (RCPSP) with stochastic activity durations invol...
We consider the Resource-Constrained Project Scheduling Problem with minimal and maximal time lags u...
Uncertainty in activity durations is a key characteristic of many real world scheduling problems in ...
In real-world project scheduling applications, activity durations are often uncertain. Proactive sch...
Abstract. In the context of Scheduling under uncertainty, Partial Order Schedules (POS) provide a co...
In this paper, we propose an extended local search frame-work to solve combinatorial optimization pr...
The purpose of this paper is to propose models for project scheduling when there is considerable unc...
AbstractLogistics project scheduling problem in indeterminate environment is gaining more and more a...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...
Robustness is essential for schedules if they are being executed under uncertain conditions. In this...