Summary Report, Central Arizona Project with Federal Prepayment Power Arrangements, February 1967, page 13early years. Following 1990, it is expected that commercial power sales would increase gradually as project water supply and associated project pumping power requirements decrease. By the year 2030 it is estimated that commercial sales would average 179,000 kilowatts. For purposes of deriving power prepayment cost estimates, it was assumed that a large, coal-fired powerplant would be located near Page, Arizona, adjacent to Lake Powell. Such a plant would burn coal obtained from the Black Mesa fields in northeastern Arizona. Sufficient transmission costs were included in the estimates to provide for proper connection of the plant to t...