The resource-constrained project scheduling problem (RCPSP) with stochastic activity durations involves the determination of a proactive schedule. Due to the non-deterministic activity durations, the real executed schedule may differ from the planned schedule. A desirable characteristic of a proactive schedule is to have small deviations between real and planned schedules. This characteristic has been named in the literature as solution robustness. We propose a chance-constrained programming model that considers the robustness level as a constraint.status: publishe
The resource-constrained project scheduling problem involves the determination of a schedule of the ...
The chance-constrained resource-constrained project scheduling problem (C-CRCPSP) is a generalizatio...
The resource-constrained project scheduling problem (RCPSP) has been widely studied during the last ...
Research concerning project planning under uncertainty has primarily focused on the stochastic resou...
The purpose of this research is to develop a new procedure for generating a proactive baseline sched...
The chance-constrained resource-constrained project scheduling problem (CC RCPSP) is the problem of ...
Uncertainty has become an inevitable aspect of project scheduling. We study the resource-constrained...
The resource-constrained project scheduling problem (RCPSP) has been widely studied. A fundamental a...
International audienceIn this chapter, we examine the RCPSP for the case when there is considerable ...
© 2017 Elsevier Ltd In this paper, we consider Resource Constrained Project Scheduling Problems (RCP...
The Resource-Constrained Project Scheduling Problem (RCPSP) has been widely studied. A fundamental a...
Uncertainty has become an inevitable aspect of project scheduling. We study the resource-constrained...
The purpose of this paper is to propose models for project scheduling when there is considerable unc...
The well-known deterministic resource-constrained project scheduling problem (RCPSP) involves the de...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...
The resource-constrained project scheduling problem involves the determination of a schedule of the ...
The chance-constrained resource-constrained project scheduling problem (C-CRCPSP) is a generalizatio...
The resource-constrained project scheduling problem (RCPSP) has been widely studied during the last ...
Research concerning project planning under uncertainty has primarily focused on the stochastic resou...
The purpose of this research is to develop a new procedure for generating a proactive baseline sched...
The chance-constrained resource-constrained project scheduling problem (CC RCPSP) is the problem of ...
Uncertainty has become an inevitable aspect of project scheduling. We study the resource-constrained...
The resource-constrained project scheduling problem (RCPSP) has been widely studied. A fundamental a...
International audienceIn this chapter, we examine the RCPSP for the case when there is considerable ...
© 2017 Elsevier Ltd In this paper, we consider Resource Constrained Project Scheduling Problems (RCP...
The Resource-Constrained Project Scheduling Problem (RCPSP) has been widely studied. A fundamental a...
Uncertainty has become an inevitable aspect of project scheduling. We study the resource-constrained...
The purpose of this paper is to propose models for project scheduling when there is considerable unc...
The well-known deterministic resource-constrained project scheduling problem (RCPSP) involves the de...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...
The resource-constrained project scheduling problem involves the determination of a schedule of the ...
The chance-constrained resource-constrained project scheduling problem (C-CRCPSP) is a generalizatio...
The resource-constrained project scheduling problem (RCPSP) has been widely studied during the last ...