MIT-IBM engineering concurrence has been reached on requests for DC buildings, equipment cooling, lighting and power generation for the production systems. These requests were subsequently issued as Lincoln Technical Information Releases by the Production Coordination Office. A proposal to provide duplex equipment similar to AN/FSQ-7 for the air division Combat Center has been furnished to ADC. Initial period of operation for the SAGE System will have maintenance services and spare parts supplied under contract with IBM
Present: J. W. Forrester, D. R. Brown, S. H. Dodd, R. R. Everett, A. P. Kromer, J. C. Proctor, N. H....
Minutes of a Joint MIT - IBM Conference held at Hartford, Connecticut on January 20, 1953. The purp...
Present: J. W. Forrester, D. R. Brown, S. H. Dodd, R. R. Everett, A. P. Kromer, J. C. Proctor, N. H....
Discusses construction of the XD-1 prototype system, engineering refinement of design, initial insta...
Principal work during this period has been concerned with the display systems development and reduct...
In the initial month following issuance of letter of intent considerable interchange of engineering ...
The third month of the interval covered by the Subcontract between MIT and IBM has continued discuss...
Collaboration between Lincoln and IBM engineering groups has continued on all phases of development ...
Joint engineering activity has resulted in engineering concurrence and Lincoln approval of additiona...
This memorandum outlines procedures for communication between MIT and IBM for work on the AN/FSQ-7 P...
Specifications for the display system, the power system and the internal memory will be prepared. Ou...
A conference reached agreement on the display specifications. They are presently being written up fo...
The continued engineering work on AN/FSQ-7 equipment during this period has covered considerable act...
Present: (IBM) B. Housman, R. W. Lowrie, R. C. Marden, D. C. Ross, C. E. Walston; (MIT) J. Giordano,...
The second month of the period covered by the MIT subcontract has seen the continuation of discussio...
Present: J. W. Forrester, D. R. Brown, S. H. Dodd, R. R. Everett, A. P. Kromer, J. C. Proctor, N. H....
Minutes of a Joint MIT - IBM Conference held at Hartford, Connecticut on January 20, 1953. The purp...
Present: J. W. Forrester, D. R. Brown, S. H. Dodd, R. R. Everett, A. P. Kromer, J. C. Proctor, N. H....
Discusses construction of the XD-1 prototype system, engineering refinement of design, initial insta...
Principal work during this period has been concerned with the display systems development and reduct...
In the initial month following issuance of letter of intent considerable interchange of engineering ...
The third month of the interval covered by the Subcontract between MIT and IBM has continued discuss...
Collaboration between Lincoln and IBM engineering groups has continued on all phases of development ...
Joint engineering activity has resulted in engineering concurrence and Lincoln approval of additiona...
This memorandum outlines procedures for communication between MIT and IBM for work on the AN/FSQ-7 P...
Specifications for the display system, the power system and the internal memory will be prepared. Ou...
A conference reached agreement on the display specifications. They are presently being written up fo...
The continued engineering work on AN/FSQ-7 equipment during this period has covered considerable act...
Present: (IBM) B. Housman, R. W. Lowrie, R. C. Marden, D. C. Ross, C. E. Walston; (MIT) J. Giordano,...
The second month of the period covered by the MIT subcontract has seen the continuation of discussio...
Present: J. W. Forrester, D. R. Brown, S. H. Dodd, R. R. Everett, A. P. Kromer, J. C. Proctor, N. H....
Minutes of a Joint MIT - IBM Conference held at Hartford, Connecticut on January 20, 1953. The purp...
Present: J. W. Forrester, D. R. Brown, S. H. Dodd, R. R. Everett, A. P. Kromer, J. C. Proctor, N. H....