This research introduces novel control metrics for projects that use cost and/or time incentives. The proposed technique extends the traditional earned value management (EV M) methodology for project control. This is done by measuring the deviation in the accrual of incentives, rather than the time and cost performance relative to the planned schedule. The proposed dedicated approach avoids two key issues when controlling incentivized projects using traditional earned value management. Firstly, the impact of variations in the cost and time dimensions are adequately weighted in the control signals. Secondly, the technique is capable of monitoring the potential non-linear accrual of incentive amounts throughout the project. The performance of...
This paper discusses the difficulty of controlling complex engineering projects with the help of the...
It is well-known that well managed and controlled projects are more likely to be delivered on time a...
The application of earned value based metrics in Serbia lags significantly behind other developed ec...
This research introduces novel control metrics for projects that use cost and/or time incentives. Th...
This research introduces novel control metrics for projects that use cost and/or time incentives. Th...
Project control has been a research topic since decades that attracts both academics and practitione...
The earned value management is a powerful and important technique in analyzing and controlling the ...
Abstract: Earned Value is a well-known project management tool that uses information on cost, schedu...
The earned value is a leading technique in monitoring and analyzing project performance and project ...
In spite of the advancements made in the Earned Schedule addition to Earned Value Management practic...
Planning, controlling, monitoring progress are key management functions for effective implementation...
According to the Project Management Institute (PMI) project management consists of planning, organiz...
AbstractEarned value project management is a well-known management system that integrates cost, sche...
Appropriate control methods are needed to anticipate potential problems and make construction projec...
We propose new metrics to integrate Earned Value Management (EVM) and Project Risk Management method...
This paper discusses the difficulty of controlling complex engineering projects with the help of the...
It is well-known that well managed and controlled projects are more likely to be delivered on time a...
The application of earned value based metrics in Serbia lags significantly behind other developed ec...
This research introduces novel control metrics for projects that use cost and/or time incentives. Th...
This research introduces novel control metrics for projects that use cost and/or time incentives. Th...
Project control has been a research topic since decades that attracts both academics and practitione...
The earned value management is a powerful and important technique in analyzing and controlling the ...
Abstract: Earned Value is a well-known project management tool that uses information on cost, schedu...
The earned value is a leading technique in monitoring and analyzing project performance and project ...
In spite of the advancements made in the Earned Schedule addition to Earned Value Management practic...
Planning, controlling, monitoring progress are key management functions for effective implementation...
According to the Project Management Institute (PMI) project management consists of planning, organiz...
AbstractEarned value project management is a well-known management system that integrates cost, sche...
Appropriate control methods are needed to anticipate potential problems and make construction projec...
We propose new metrics to integrate Earned Value Management (EVM) and Project Risk Management method...
This paper discusses the difficulty of controlling complex engineering projects with the help of the...
It is well-known that well managed and controlled projects are more likely to be delivered on time a...
The application of earned value based metrics in Serbia lags significantly behind other developed ec...