814060PDFResearch PaperContractsRoad constructionKentuckyHancher, Donn E.Werkmeister Jr., Raymond F.University of Kentucky Transportation CenterUniversity of KentuckyNTL-INTELLIGENT TRANSPORTATION SYSTEMS-INTELLIGENT TRANSPORTATION SYSTEMSUS Transportation CollectionThis research project was to update the KyTC's planning tool used for the determination of contract time allotted for contractors to complete highway construction projects in the Commonwealth of Kentucky. Although this issue was initially raised by the Transportation Cabinet, the FHWA has also expressed a desire to have all states use an organized rationale for determining and documenting their determination of allotted contract time for their highway construction projects. Addi...
State departments of transportation (DOTs) are expanding the use of electronic engineering data (EED...
Kentucky Transportation Cabinet (KYTC) Project Managers bear responsibility for preparing all phases...
1. PURPOSE. To provide procedures for determining contract time for construction projects. 2. POLICY...
This paper reports on the results of research that was funded by the Kentucky Transportation Cabinet...
Phase I of this study was funded by OTC and was successfully completed in December, 2006. In phase I...
PDFTech Report29694-7SSContract ratesSoftwareContract administrationConstructionQuality controlPrequ...
Final report.PDFTech ReportFHWA-OK-08-02ODOT Reference 3459014260ODOT Job Piece 01946(48)Road constr...
Overseeing the delivery of highway projects at the Kentucky Transportation Cabinet (KYTC) requires t...
The Federal Highway Administration requires State Transportation Agencies to have a formal method to...
Production rates are significantly important for contract time determination procedures as these are...
https://doi.org/10.13023/KTC.RR.2017.12PDFTech ReportKTC-17-12/SPR13-460-1FSPR 13-460Economic analys...
The Critical Path Method is a proven management technique used for determining the critical activiti...
US Transportation Collection2020PDFTech ReportJentink, RossBossert, JustinJones, HeatherWSB & Associ...
Contract time, is the maximum time allowed for completion of all work described in contract document...
Estimating the cost of highway construction projects is among the more challenging tasks state trans...
State departments of transportation (DOTs) are expanding the use of electronic engineering data (EED...
Kentucky Transportation Cabinet (KYTC) Project Managers bear responsibility for preparing all phases...
1. PURPOSE. To provide procedures for determining contract time for construction projects. 2. POLICY...
This paper reports on the results of research that was funded by the Kentucky Transportation Cabinet...
Phase I of this study was funded by OTC and was successfully completed in December, 2006. In phase I...
PDFTech Report29694-7SSContract ratesSoftwareContract administrationConstructionQuality controlPrequ...
Final report.PDFTech ReportFHWA-OK-08-02ODOT Reference 3459014260ODOT Job Piece 01946(48)Road constr...
Overseeing the delivery of highway projects at the Kentucky Transportation Cabinet (KYTC) requires t...
The Federal Highway Administration requires State Transportation Agencies to have a formal method to...
Production rates are significantly important for contract time determination procedures as these are...
https://doi.org/10.13023/KTC.RR.2017.12PDFTech ReportKTC-17-12/SPR13-460-1FSPR 13-460Economic analys...
The Critical Path Method is a proven management technique used for determining the critical activiti...
US Transportation Collection2020PDFTech ReportJentink, RossBossert, JustinJones, HeatherWSB & Associ...
Contract time, is the maximum time allowed for completion of all work described in contract document...
Estimating the cost of highway construction projects is among the more challenging tasks state trans...
State departments of transportation (DOTs) are expanding the use of electronic engineering data (EED...
Kentucky Transportation Cabinet (KYTC) Project Managers bear responsibility for preparing all phases...
1. PURPOSE. To provide procedures for determining contract time for construction projects. 2. POLICY...