Cost growth is a problem in U.S. Department of Defense (DoD) acquisitions. A particular component of cost growth is a cost overrun or Over Target Baseline (OTB). In 2009, Trahan found that the Gompertz growth curve better predicted program Estimates at Completion (EAC) for OTB contracts. In 2010, Thickstun studied “the relationships between overruns and a variety of factors,” but found OTB occurrences “random” and questioned the benefit of the OTB process (Thickstun, 2010). In this research, we study OTB‟s ability to effect improved program cost performance; we examine OTB‟s effect on the cumulative Cost Performance Index (CPI) slope after an OTB intervention. We find there is no statistically significant change in cumulative CPI slope afte...
Student Research Poster ShowThe purpose of this research is to demonstrate the economic effects that...
Determining accurate cost and schedule is a crucial step to planning acquisition expenditures but hi...
Historically, cost growth regression models analyze aggregate, program-level information. Initiative...
Cost estimators use a variety of methods to develop estimates at completion (EACs) and new methods c...
Efficient decision making mandates the accuracy of forecasted estimations of a contract\u27s final v...
This thesis explores the assumption that cost overruns are related to contract changes. A common ass...
Government contractors report earned value (EV) information to government agencies in monthly Contra...
different angles have been looked at to try and discover how to better estimate cost, what causes co...
David McNicol, in "Post-Milestone B Funding Climate and Cost Growth in Major Defense Acquisition Pro...
The concept of a Cost Performance Index (CPI) stability rule originated with the seminal article fro...
The United States Air Force (USAF) has outsourced a significant portion of their activities defined ...
This article examines how cost growth factors (CGF) change over a program’s acquisition life cycle f...
This study sought to predict cost growth in major Department of Defense (DoD) acquisition programs u...
For decades, operation and maintenance (O&M) has been growing as a share of the defense budget. To u...
Previous studies have linked human capital with performance. The studies have shown performance, mea...
Student Research Poster ShowThe purpose of this research is to demonstrate the economic effects that...
Determining accurate cost and schedule is a crucial step to planning acquisition expenditures but hi...
Historically, cost growth regression models analyze aggregate, program-level information. Initiative...
Cost estimators use a variety of methods to develop estimates at completion (EACs) and new methods c...
Efficient decision making mandates the accuracy of forecasted estimations of a contract\u27s final v...
This thesis explores the assumption that cost overruns are related to contract changes. A common ass...
Government contractors report earned value (EV) information to government agencies in monthly Contra...
different angles have been looked at to try and discover how to better estimate cost, what causes co...
David McNicol, in "Post-Milestone B Funding Climate and Cost Growth in Major Defense Acquisition Pro...
The concept of a Cost Performance Index (CPI) stability rule originated with the seminal article fro...
The United States Air Force (USAF) has outsourced a significant portion of their activities defined ...
This article examines how cost growth factors (CGF) change over a program’s acquisition life cycle f...
This study sought to predict cost growth in major Department of Defense (DoD) acquisition programs u...
For decades, operation and maintenance (O&M) has been growing as a share of the defense budget. To u...
Previous studies have linked human capital with performance. The studies have shown performance, mea...
Student Research Poster ShowThe purpose of this research is to demonstrate the economic effects that...
Determining accurate cost and schedule is a crucial step to planning acquisition expenditures but hi...
Historically, cost growth regression models analyze aggregate, program-level information. Initiative...