Looking downstream from canal Station 50+00. Most of the present canal construction seen in aboe photo has been performed during this construction season. work is being performed by A & B Construction Company under Specification no. DC-5464
Upstream view from canal station 44+00/ Concrete lining opearations are in progress. Work is bing pe...
View looking south at division box at Station 323+47. Canal is in background looking downstream. Wor...
Looking upstream from canal Station 300+00 at embankment progress. Contractor is presently working o...
Upstream view of canal embankment progress from canal Station 311+00. Work is being done by A & B co...
Looking downstream from station 552+00 at recently completed canal excavation. Work being done by A ...
Looking downstream at canal excavation from station 555+50. Work being done by A & B Construction Co...
Looking downstream from canal station 109+00 at embankment construction and canal excavation. Work i...
Looking upstream from Station 542+00 showing general condition of partially complete canal. Work bei...
Looking downstream from station 604+00 at typical operation of building up canal banks. Work is bein...
Looking upstream from canal Station 300+50 at embankment progress. Work is being done by A & B Const...
Looking downstream from Station 558+00 at incomplete canal. Work is being done by A & B Construction...
Looking upstream feom canal station 143+00 at earth lining nearing completion. Work is being perform...
Looking upstream at canal prism from Station 558+00. Water in canal prism occurred from overflowing ...
Looking downstream from station 464+06 at recently completed canal trimming. Note soil on both banks...
Looking downstream from canal Station 558+00 at canal construction. No activity has been performed i...
Upstream view from canal station 44+00/ Concrete lining opearations are in progress. Work is bing pe...
View looking south at division box at Station 323+47. Canal is in background looking downstream. Wor...
Looking upstream from canal Station 300+00 at embankment progress. Contractor is presently working o...
Upstream view of canal embankment progress from canal Station 311+00. Work is being done by A & B co...
Looking downstream from station 552+00 at recently completed canal excavation. Work being done by A ...
Looking downstream at canal excavation from station 555+50. Work being done by A & B Construction Co...
Looking downstream from canal station 109+00 at embankment construction and canal excavation. Work i...
Looking upstream from Station 542+00 showing general condition of partially complete canal. Work bei...
Looking downstream from station 604+00 at typical operation of building up canal banks. Work is bein...
Looking upstream from canal Station 300+50 at embankment progress. Work is being done by A & B Const...
Looking downstream from Station 558+00 at incomplete canal. Work is being done by A & B Construction...
Looking upstream feom canal station 143+00 at earth lining nearing completion. Work is being perform...
Looking upstream at canal prism from Station 558+00. Water in canal prism occurred from overflowing ...
Looking downstream from station 464+06 at recently completed canal trimming. Note soil on both banks...
Looking downstream from canal Station 558+00 at canal construction. No activity has been performed i...
Upstream view from canal station 44+00/ Concrete lining opearations are in progress. Work is bing pe...
View looking south at division box at Station 323+47. Canal is in background looking downstream. Wor...
Looking upstream from canal Station 300+00 at embankment progress. Contractor is presently working o...