In this presentation we propose a method for dealing with uncertainty in the resource-constrained multi-project planning (RCCP) problem, by incorporating stochasticity. This tactical planning level is typically characterized by many uncertainties, such as processing time uncertainty, project release date delay, network uncertainty, rush orders, resource availability, project scenarios, etc. So far
We define and develop a solution approach for planning, scheduling and managing project efforts wher...
We consider a scheduling problem where each job requires multiple classes of resources, which we ref...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...
At the tactical planning level in a multi-project environment, uncertainties are inherent to the wor...
Dealing with uncertainties in multi-project rough-cut capacity planning is the topic of this paper. ...
Research concerning project planning under uncertainty has primarily focused on the stochastic resou...
This chapter studies the incorporation of uncertainty into multi-project rough-cut capacity planning...
Project planning and scheduling when there are both resource constraints and uncertainty in task dur...
Resource constraints frequently complicate multi-agent planning problems. Existing algorithms for re...
This paper is concerned with a simulation study for a stochastic production network model, where the...
Copyright (2012) FU Na Resource Constrained Project Scheduling Problems with minimum and maximum tim...
The extant literature offers little basis for uncertainty analysis of resource acquisition in projec...
We investigate project scheduling with stochastic activity durations to maximize the expected net pr...
Resource constraints frequently complicate multi-agent planning problems. Existing algorithms for re...
International audienceIn this chapter, we examine the RCPSP for the case when there is considerable ...
We define and develop a solution approach for planning, scheduling and managing project efforts wher...
We consider a scheduling problem where each job requires multiple classes of resources, which we ref...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...
At the tactical planning level in a multi-project environment, uncertainties are inherent to the wor...
Dealing with uncertainties in multi-project rough-cut capacity planning is the topic of this paper. ...
Research concerning project planning under uncertainty has primarily focused on the stochastic resou...
This chapter studies the incorporation of uncertainty into multi-project rough-cut capacity planning...
Project planning and scheduling when there are both resource constraints and uncertainty in task dur...
Resource constraints frequently complicate multi-agent planning problems. Existing algorithms for re...
This paper is concerned with a simulation study for a stochastic production network model, where the...
Copyright (2012) FU Na Resource Constrained Project Scheduling Problems with minimum and maximum tim...
The extant literature offers little basis for uncertainty analysis of resource acquisition in projec...
We investigate project scheduling with stochastic activity durations to maximize the expected net pr...
Resource constraints frequently complicate multi-agent planning problems. Existing algorithms for re...
International audienceIn this chapter, we examine the RCPSP for the case when there is considerable ...
We define and develop a solution approach for planning, scheduling and managing project efforts wher...
We consider a scheduling problem where each job requires multiple classes of resources, which we ref...
The resource constrained project scheduling problem (RCPSP) has been an important research topic ove...