The new dam at Mont Cenis has increased to water volume in the reservoir from 32 to 320 million m3 and provides a potential energy of 650.000 million Mp x m. This article describes the work involved in the construction of this project. Among other features, the water has been led to the reservoir along a network of varying cross-section, and of 28 km total length. The pressure conduit has been designed for a flow rate of 51 m3/s, its diameter varying between 4 and 5 m. The new power stations at Villarodin are fed by a pipe 3.6 km in length and 3 m in diameter. This conduit runs along a trench and is isolated from the ground, because of the gypsum and anhydrites contained in the soil. Its weight is 10.000 Mp, which is a European record. Th...