A circular excavation, 117 feet (36 m) in diameter by 90 feet (27 m) deep, was designed by an experienced engineering firm and construction was performed by an experienced contractor. Nevertheless, the excavation support system suffered a complete collapse long before the maximum depth was reached. The failure is described and its causes are discussed
A 16m deep sheeted excavation failed by piping of the base. The sequence of events leading to this f...
This case history presents, from a geotechnical engineer\u27s viewpoint, various technical, budgetar...
A compacted silty clay containment dike for a waste slurry holding pond, with a design height of 44 ...
The design, construction, and collapse of an excavation support system constructed through layered s...
During the construction of Contract C824 of the Circle Line in Singapore, on 20th April 2004 an 80 m...
One of the largest development projects in the City of Beirut involved the excavation of an area of ...
On 3 October 2013, a global failure occurred in one of the stabilised sections of a deep excavation ...
A cantilever retaining wall, designed in apparent accord with provisions in a civil engineering hand...
A building collapse is investigated in which a shallow trench, excavated along the length of the bui...
In June of 1994 a 20-m section of 1.4-m diameter, restrained-joint, ductile iron pipe failed during ...
On 6th of January 2001, a fill slope collapsed in Putrajaya, Malaysia. The failed slope was 25m in h...
Rock excavation for a 7,200-square-meter building site in Saudi Arabia intercepted a large cavity un...
As an embankment was constructed on thick soft clay ground, a deep seated failure took place. A larg...
In July 1991, the intake and discharge pipelines of a major power plant collapsed. A 60-ft. deep exc...
Excavation for Boston’s Central Artery project included one of the most interesting temporary excava...
A 16m deep sheeted excavation failed by piping of the base. The sequence of events leading to this f...
This case history presents, from a geotechnical engineer\u27s viewpoint, various technical, budgetar...
A compacted silty clay containment dike for a waste slurry holding pond, with a design height of 44 ...
The design, construction, and collapse of an excavation support system constructed through layered s...
During the construction of Contract C824 of the Circle Line in Singapore, on 20th April 2004 an 80 m...
One of the largest development projects in the City of Beirut involved the excavation of an area of ...
On 3 October 2013, a global failure occurred in one of the stabilised sections of a deep excavation ...
A cantilever retaining wall, designed in apparent accord with provisions in a civil engineering hand...
A building collapse is investigated in which a shallow trench, excavated along the length of the bui...
In June of 1994 a 20-m section of 1.4-m diameter, restrained-joint, ductile iron pipe failed during ...
On 6th of January 2001, a fill slope collapsed in Putrajaya, Malaysia. The failed slope was 25m in h...
Rock excavation for a 7,200-square-meter building site in Saudi Arabia intercepted a large cavity un...
As an embankment was constructed on thick soft clay ground, a deep seated failure took place. A larg...
In July 1991, the intake and discharge pipelines of a major power plant collapsed. A 60-ft. deep exc...
Excavation for Boston’s Central Artery project included one of the most interesting temporary excava...
A 16m deep sheeted excavation failed by piping of the base. The sequence of events leading to this f...
This case history presents, from a geotechnical engineer\u27s viewpoint, various technical, budgetar...
A compacted silty clay containment dike for a waste slurry holding pond, with a design height of 44 ...