This report documents an energy audit performed by Pacific Northwest National Laboratory (PNNL) and Redhorse Corporation (Redhorse) conducted on the Federal Aviation Administration (FAA) control tower and base building in Boise, Idaho. This report presents findings of the energy audit team that evaluated construction documents and operating specifications (at the 100% level) followed by a site visit of the facility under construction. The focus of the review was to identify measures that could be incorporated into the final design and operating specifications that would result in additional energy savings for FAA that would not have otherwise occurred
The goal of the U.S. Department of Energy (DOE) Federal Energy Management Program (FEMP) is to facil...
A partial commissioning and energy audit were performed on a recently constructed building at the Un...
Energy audits are a powerful tool for uncovering operational and equipment improvements that will sa...
Pacific Northwest National Laboratory (PNNL) and Redhorse Corporation (Redhorse) conducted an energy...
This report represents findings of a design review team that evaluated construction documents (at th...
This report represents findings of a design review team that evaluated construction documents (at th...
This report represents findings of a design review team that evaluated construction documents (at th...
A building energy assessment was performed by a team of engineers from Pacific Northwest National La...
A building energy audit was performed by a team of engineers from Pacific Northwest National Laborat...
The American Recovery and Reinvestment Act of 2009 (Recovery Act) highlighted the importance of redu...
Report describing a building retuning workshop presented to staff at Redstone Arsenal. Document incl...
A detailed energy assessment was performed by a team of engineers from Pacific Northwest National La...
This report documents the findings of an on-site audit of the U.S. Customs Cargo Inspection Facility...
This report documents the findings from an onsite audit of the John W. Bricker Federal building loca...
Snohomish County Public Utilities District (the District or Snohomish PUD) provides electricity to a...
The goal of the U.S. Department of Energy (DOE) Federal Energy Management Program (FEMP) is to facil...
A partial commissioning and energy audit were performed on a recently constructed building at the Un...
Energy audits are a powerful tool for uncovering operational and equipment improvements that will sa...
Pacific Northwest National Laboratory (PNNL) and Redhorse Corporation (Redhorse) conducted an energy...
This report represents findings of a design review team that evaluated construction documents (at th...
This report represents findings of a design review team that evaluated construction documents (at th...
This report represents findings of a design review team that evaluated construction documents (at th...
A building energy assessment was performed by a team of engineers from Pacific Northwest National La...
A building energy audit was performed by a team of engineers from Pacific Northwest National Laborat...
The American Recovery and Reinvestment Act of 2009 (Recovery Act) highlighted the importance of redu...
Report describing a building retuning workshop presented to staff at Redstone Arsenal. Document incl...
A detailed energy assessment was performed by a team of engineers from Pacific Northwest National La...
This report documents the findings of an on-site audit of the U.S. Customs Cargo Inspection Facility...
This report documents the findings from an onsite audit of the John W. Bricker Federal building loca...
Snohomish County Public Utilities District (the District or Snohomish PUD) provides electricity to a...
The goal of the U.S. Department of Energy (DOE) Federal Energy Management Program (FEMP) is to facil...
A partial commissioning and energy audit were performed on a recently constructed building at the Un...
Energy audits are a powerful tool for uncovering operational and equipment improvements that will sa...