Inspired by risk-sensitive, robust scheduling for planetary rovers under temporal uncertainty, this work introduces the Probabilistic Simple Temporal Network with Uncertainty (PSTNU), a temporal planning formalism that unifies the set-bounded and probabilistic temporal uncertainty models from the STNU and PSTN literature. By allowing any combination of these two types of uncertainty models, PSTNU's can more appropriately reflect the varying levels of knowledge that a mission operator might have regarding the stochastic duration models of different activities. We also introduce PARIS, a novel sound and provably polynomial-time algorithm for risk-sensitive strong scheduling of PSTNU's. Due to its fully linear problem encoding for typical temp...
In this work we treat the problem of scheduling under two types of temporal uncertainty, setbased an...
Flexibility in agent scheduling increases the resilience of temporal plans in the face of new constr...
In real-world project scheduling applications, activity durations are often uncertain. Proactive sch...
Inspired by risk-sensitive, robust scheduling for planetary rovers under temporal uncertainty, this ...
Inspired by risk-sensitive, robust scheduling for planetary rovers under temporal uncertainty, this ...
Scheduling under uncertainty is essential to many autonomous systems and logistics tasks. Probabilis...
Scheduling under uncertainty is essential to many au-tonomous systems and logistics tasks. Probabili...
Most existing works in Probabilistic Simple Temporal Networks (PSTNs) base their frameworks on well-...
In Temporal Planning a typical assumption is that the agent controls the execution time of all event...
Probabilistic Simple Temporal Networks (PSTN) are used to represent scheduling problems under uncert...
The controllability of a temporal network is defined as an agent's ability to navigate around the un...
Probabilistic Simple Temporal Networks (PSTN) are used to represent scheduling problems under uncert...
Simple Temporal Networks (STNs) have proved useful in ap-plications that involve metric time. Howeve...
AbstractComplex real-world systems consist of collections of interacting processes/events. These pro...
MEng thesisTemporal uncertainty arises when performing any activity in the natural world. When activ...
In this work we treat the problem of scheduling under two types of temporal uncertainty, setbased an...
Flexibility in agent scheduling increases the resilience of temporal plans in the face of new constr...
In real-world project scheduling applications, activity durations are often uncertain. Proactive sch...
Inspired by risk-sensitive, robust scheduling for planetary rovers under temporal uncertainty, this ...
Inspired by risk-sensitive, robust scheduling for planetary rovers under temporal uncertainty, this ...
Scheduling under uncertainty is essential to many autonomous systems and logistics tasks. Probabilis...
Scheduling under uncertainty is essential to many au-tonomous systems and logistics tasks. Probabili...
Most existing works in Probabilistic Simple Temporal Networks (PSTNs) base their frameworks on well-...
In Temporal Planning a typical assumption is that the agent controls the execution time of all event...
Probabilistic Simple Temporal Networks (PSTN) are used to represent scheduling problems under uncert...
The controllability of a temporal network is defined as an agent's ability to navigate around the un...
Probabilistic Simple Temporal Networks (PSTN) are used to represent scheduling problems under uncert...
Simple Temporal Networks (STNs) have proved useful in ap-plications that involve metric time. Howeve...
AbstractComplex real-world systems consist of collections of interacting processes/events. These pro...
MEng thesisTemporal uncertainty arises when performing any activity in the natural world. When activ...
In this work we treat the problem of scheduling under two types of temporal uncertainty, setbased an...
Flexibility in agent scheduling increases the resilience of temporal plans in the face of new constr...
In real-world project scheduling applications, activity durations are often uncertain. Proactive sch...