Highway construction efficiency is critical to highway users such as the trucking industry given today’s era of shortages in funding, and given the need for major re-investments in the highway system. One topic that can add to project costs relates to delays and how contractors are reimbursed for such delays. Delays are common in construction, especially in complex heavy highway and other infrastructure projects, and the claims they generate have negative effects on project schedules and costs. In spite of this, the analysis of claims is hindered due to the variety of methods and analysis techniques in use and lack of standardization in the incorporation of delay claim analysis methods in construction contracts. This paper reviews different...
Many factors, such as unforeseeable events, managerial and financial problems of contractors, insuff...
Delayed completion of a construction project is often caused by a complex interaction of a combinati...
In Road and Bridge construction projects, delay could be defined as the time overrun either beyond c...
2014 Spring.Delay-caused claims lead to cost overruns in infrastructure projects due to the cost of ...
Today\u27s construction industry is fast paced, complex, and expensive. Unfortunately, there exist m...
Abstract: The purpose of this research was to provide an understanding of what causes delays and cla...
Due to the character of the original source materials and the nature of batch digitization, quality ...
Road and highway construction projects are plagued by unanticipated conditions and changes, which ca...
As in any other construction works, road construction contracts are liable to various kinds of delay...
This thesis was submitted for the award of Doctor of Philosophy and was awarded by Brunel University...
The timely completion of highway construction projects is an important SHA objective. A significant ...
Abstract- Nowadays, highway construction suffers from delay and cost overruns, which causes traffic ...
Construction projects are complex, from their design to the execution phase. Delivering a project on...
Disputes in the construction industry originate primarily from the occurrence of delays, which are t...
The problem of delay in construction industry is a regular phenomenon worldwide, and construction in...
Many factors, such as unforeseeable events, managerial and financial problems of contractors, insuff...
Delayed completion of a construction project is often caused by a complex interaction of a combinati...
In Road and Bridge construction projects, delay could be defined as the time overrun either beyond c...
2014 Spring.Delay-caused claims lead to cost overruns in infrastructure projects due to the cost of ...
Today\u27s construction industry is fast paced, complex, and expensive. Unfortunately, there exist m...
Abstract: The purpose of this research was to provide an understanding of what causes delays and cla...
Due to the character of the original source materials and the nature of batch digitization, quality ...
Road and highway construction projects are plagued by unanticipated conditions and changes, which ca...
As in any other construction works, road construction contracts are liable to various kinds of delay...
This thesis was submitted for the award of Doctor of Philosophy and was awarded by Brunel University...
The timely completion of highway construction projects is an important SHA objective. A significant ...
Abstract- Nowadays, highway construction suffers from delay and cost overruns, which causes traffic ...
Construction projects are complex, from their design to the execution phase. Delivering a project on...
Disputes in the construction industry originate primarily from the occurrence of delays, which are t...
The problem of delay in construction industry is a regular phenomenon worldwide, and construction in...
Many factors, such as unforeseeable events, managerial and financial problems of contractors, insuff...
Delayed completion of a construction project is often caused by a complex interaction of a combinati...
In Road and Bridge construction projects, delay could be defined as the time overrun either beyond c...