This research aims to understand the process of progress reporting and forecasting project status of different future targeted dates. The study focuses mainly on trending and time/Cost control of engineering, procurement and construction (EPC) project. A field study of the practices of the industrial collaborator (SNC-Lavalin), along with related materials from the literature, is conducted and documented. This research presents a model for improving trending and forecasting of time and cost in construction operations. The proposed model has 3 main functions: (1) trend estimate accuracy, (2) project progress integrated control and forecasting, and (3) progress visualization database. @Risk 5.0 for excel, Windows SharePoint Server and visual...
from the thesis or use of any of the information contained in it must acknowledge this thesis as the...
Successful construction project management and control is highly dependent on information. Early det...
201 p.Thesis (Ph.D.)--University of Illinois at Urbana-Champaign, 2007.Using the proposed models, pr...
Precise and accurate prediction models for duration and cost enable contractors to improve their dec...
Project monitoring involves collecting the actual‐progress data, and comparing them against the rele...
Planning, controlling, monitoring progress are key management functions for effective implementation...
Project progress is an apprehension for every project, as it indicates how the project is likely to ...
Controlling construction projects necessitates controlling their time and cost in an effort to meet ...
Since project control involves taking decisions that affect the future, the ability to accurately fo...
Measuring actual project progress and comparing it with the planned time schedule is essential in co...
Projects in the construction industry struggle to meet set goals. This is especially true in long te...
Project progress is an apprehension for every project, as it indicates how the project is likely to ...
This paper presents a new forecasting model to improve Earned Value (EV) method of projects. This me...
This study demonstrates the application of design principles for tools in Engineering, Procurement, ...
The aim of this research was to improve the quantitative support to project planning and control pri...
from the thesis or use of any of the information contained in it must acknowledge this thesis as the...
Successful construction project management and control is highly dependent on information. Early det...
201 p.Thesis (Ph.D.)--University of Illinois at Urbana-Champaign, 2007.Using the proposed models, pr...
Precise and accurate prediction models for duration and cost enable contractors to improve their dec...
Project monitoring involves collecting the actual‐progress data, and comparing them against the rele...
Planning, controlling, monitoring progress are key management functions for effective implementation...
Project progress is an apprehension for every project, as it indicates how the project is likely to ...
Controlling construction projects necessitates controlling their time and cost in an effort to meet ...
Since project control involves taking decisions that affect the future, the ability to accurately fo...
Measuring actual project progress and comparing it with the planned time schedule is essential in co...
Projects in the construction industry struggle to meet set goals. This is especially true in long te...
Project progress is an apprehension for every project, as it indicates how the project is likely to ...
This paper presents a new forecasting model to improve Earned Value (EV) method of projects. This me...
This study demonstrates the application of design principles for tools in Engineering, Procurement, ...
The aim of this research was to improve the quantitative support to project planning and control pri...
from the thesis or use of any of the information contained in it must acknowledge this thesis as the...
Successful construction project management and control is highly dependent on information. Early det...
201 p.Thesis (Ph.D.)--University of Illinois at Urbana-Champaign, 2007.Using the proposed models, pr...