In recent years, considerable attention has been directed towards ascertaining the nature of disruptions in construction contracting. In practice, attempts are made to identify the causes of delays, modify the schedule by incorporating revised durations, and determine the impacts associated with the new project time. The analysis itself is usually complex and can be aided by a computerized approach. In this work, the advantages and the shortcomings of the existing delay analysis techniques are highlighted and a new delay analysis technique is developed and tested. A methodology to quantify impact costs related to loss of productivity, is also proposed and discussed. In addition, both the delay analysis technique and the cost calculation me...
This thesis was submitted for the award of Doctor of Philosophy and was awarded by Brunel University...
Delayed completion of a construction project is often caused by a complex interaction of a combinati...
Claims and disputes on time extension for delays are common in construction projects. Various method...
Many factors, such as unforeseeable events, managerial and financial problems of contractors, insuff...
Delay analysis and schedule compression are normally treated as separate, independent, aspects of th...
A review of existing literature and research findings indicated that whilst the incidence of time ex...
The construction industry is fragmented due to the many stakeholders and the diverse phases involved...
Delay is one of the major problems in construction industry. Therefore, it is common for constructio...
Delay claims are a common occurrence in construction projects. Many techniques have been developed t...
Schedule analysts often resolve diverse schedule delay problems in construction projects based on th...
Abstract: The purpose of this research was to provide an understanding of what causes delays and cla...
Construction projects are complex, from their design to the execution phase. Delivering a project on...
Due to the character of the original source materials and the nature of batch digitization, quality ...
There are three main criteria that account for a construction project’s success: completion on-time,...
Nowadays, construction delay disputes often end up on the arbitration route where the delay experts ...
This thesis was submitted for the award of Doctor of Philosophy and was awarded by Brunel University...
Delayed completion of a construction project is often caused by a complex interaction of a combinati...
Claims and disputes on time extension for delays are common in construction projects. Various method...
Many factors, such as unforeseeable events, managerial and financial problems of contractors, insuff...
Delay analysis and schedule compression are normally treated as separate, independent, aspects of th...
A review of existing literature and research findings indicated that whilst the incidence of time ex...
The construction industry is fragmented due to the many stakeholders and the diverse phases involved...
Delay is one of the major problems in construction industry. Therefore, it is common for constructio...
Delay claims are a common occurrence in construction projects. Many techniques have been developed t...
Schedule analysts often resolve diverse schedule delay problems in construction projects based on th...
Abstract: The purpose of this research was to provide an understanding of what causes delays and cla...
Construction projects are complex, from their design to the execution phase. Delivering a project on...
Due to the character of the original source materials and the nature of batch digitization, quality ...
There are three main criteria that account for a construction project’s success: completion on-time,...
Nowadays, construction delay disputes often end up on the arbitration route where the delay experts ...
This thesis was submitted for the award of Doctor of Philosophy and was awarded by Brunel University...
Delayed completion of a construction project is often caused by a complex interaction of a combinati...
Claims and disputes on time extension for delays are common in construction projects. Various method...