The electrical interconnections between the LHC main magnets are made of soldered joints (splices) of two superconducting Rutherford cables, stabilized by a copper busbar. In 2009, a number of splices was found not properly stabilized and could have suffered a thermal runaway in case of quench at high current. The LHC was, therefore, operated at reduced energy and all joints were continuously monitored by a newly installed layer of the quench protection system. During the first long shutdown (LS1) in 2013/14, the high-current busbar joints were consolidated to allow us a safe operation of the LHC at its design energy, i.e., 14-TeV center-of-mass. The superconducting magnets and circuits consolidation project has coordinated the consolidatio...
Following the analysis of the September 2008 LHC incident, the assembly process and the quality assu...
After the incident of September 2008, the operational beam energy of the LHC has been set to 3.5 TeV...
Following the analysis of the September 2008 LHC incident, the assembly process and the quality assu...
At each interconnection between LHC main magnets a low-resistance solder joint must be made between ...
The interconnections between the LHC main magnets are made of soldered joints (splices) of two super...
Following the QPS review in February 2009, a potential source of problems with the main circuit bus ...
In 2008 a defective connection in one of the 13 kA dipole circuits of the LHC caused an electric bre...
The first long shutdown (LS1) of the LHC machine at CERN started in February 2013. The main trigger ...
The interconnections between the LHC main magnets are made of soldered joints (splices) of two super...
Following the incident in one of the main dipole circuits of the Large Hadron Collider (LHC) in Sept...
To eliminate the risk of thermal runaways in LHC interconnections a consolidation by placing shunts ...
The main busbar interconnection splices of the Large Hadron Collider are assembled by inductive sold...
In 2013, a long shutdown of the Large Hadron Collider (LHC) at CERN will allow comprehensive mainten...
The incident of 19 September 2008 at the LHC was caused by a faulty inter-magnet splice of about 200...
For the consolidation of the LHC main interconnection splices it is planned to solder shunts onto ea...
Following the analysis of the September 2008 LHC incident, the assembly process and the quality assu...
After the incident of September 2008, the operational beam energy of the LHC has been set to 3.5 TeV...
Following the analysis of the September 2008 LHC incident, the assembly process and the quality assu...
At each interconnection between LHC main magnets a low-resistance solder joint must be made between ...
The interconnections between the LHC main magnets are made of soldered joints (splices) of two super...
Following the QPS review in February 2009, a potential source of problems with the main circuit bus ...
In 2008 a defective connection in one of the 13 kA dipole circuits of the LHC caused an electric bre...
The first long shutdown (LS1) of the LHC machine at CERN started in February 2013. The main trigger ...
The interconnections between the LHC main magnets are made of soldered joints (splices) of two super...
Following the incident in one of the main dipole circuits of the Large Hadron Collider (LHC) in Sept...
To eliminate the risk of thermal runaways in LHC interconnections a consolidation by placing shunts ...
The main busbar interconnection splices of the Large Hadron Collider are assembled by inductive sold...
In 2013, a long shutdown of the Large Hadron Collider (LHC) at CERN will allow comprehensive mainten...
The incident of 19 September 2008 at the LHC was caused by a faulty inter-magnet splice of about 200...
For the consolidation of the LHC main interconnection splices it is planned to solder shunts onto ea...
Following the analysis of the September 2008 LHC incident, the assembly process and the quality assu...
After the incident of September 2008, the operational beam energy of the LHC has been set to 3.5 TeV...
Following the analysis of the September 2008 LHC incident, the assembly process and the quality assu...