This thesis details the development of a post-closure management plan for a hazardous waste landfill. The cover system designed by Elias (1996) for the 1951 cell at the Massachusetts Military Reservation (MMR) located on Cape Cod, Massachusetts was used as the basis for the plan. The proposed plan satisfies the requirements for the closure/post-closure management of landfills stipulated by the state of Massachusetts. The purpose of the plan is to ensure that the cell will not contribute any further contamination to the aquifer, and to assess the cap and geomembrane performance. The management plan specifies a monitoring program for ground and surface water as well as air quality. Three monitoring wells, along with several pre-existing wells...
The area immediately surrounding a landfill was studied by DC resistivity methods, soil borings, and...
ABSTRACT The Chemical Waste Landfill (CWL) is a 1.9 acre site operated from 1962 until 1985 to dispo...
There is a finite period of time during which the plastic sheeting upper composite liner and lower p...
Thesis (M. Eng.)--Massachusetts Institute of Technology, Dept. of Civil and Environmental Engineerin...
Management of a landfill is a continuous process that proceeds long after the active landfill period...
Subtitle D of the Resource Conservation and Recovery Act (RCRA) requires a post closure period of 30...
Corrective Action Unit (CAU) 424, the Area 3 Landfill Complex at Tonopah Test Range, consists of eig...
Corrective Action Unit (CAU) 424, the Area 3 Landfill Complexes at Tonopah Test Range, consists of e...
Thesis (M. Eng.)--Massachusetts Institute of Technology, Dept. of Civil and Environmental Engineerin...
A Professional Project Report Submitted in Partial Fulfillment of the Requirements for the Degree o...
According to solid waste facility regulations codified in 40 CFR §258.61(b), the 30-year PCC period ...
This plan has been prepared in response to direction from the U.S. Department of Energy. The purpose...
Landfills remain the most frequently used method of municipal waste (MSW) disposal. Landfills are de...
This document presents an Environmental Monitoring Plan (EMP) for Waste Area Grouping (WAG 6) at Oak...
This report represents the Geotek Engineering Company, Inc., (Geotek) record of activities to suppor...
The area immediately surrounding a landfill was studied by DC resistivity methods, soil borings, and...
ABSTRACT The Chemical Waste Landfill (CWL) is a 1.9 acre site operated from 1962 until 1985 to dispo...
There is a finite period of time during which the plastic sheeting upper composite liner and lower p...
Thesis (M. Eng.)--Massachusetts Institute of Technology, Dept. of Civil and Environmental Engineerin...
Management of a landfill is a continuous process that proceeds long after the active landfill period...
Subtitle D of the Resource Conservation and Recovery Act (RCRA) requires a post closure period of 30...
Corrective Action Unit (CAU) 424, the Area 3 Landfill Complex at Tonopah Test Range, consists of eig...
Corrective Action Unit (CAU) 424, the Area 3 Landfill Complexes at Tonopah Test Range, consists of e...
Thesis (M. Eng.)--Massachusetts Institute of Technology, Dept. of Civil and Environmental Engineerin...
A Professional Project Report Submitted in Partial Fulfillment of the Requirements for the Degree o...
According to solid waste facility regulations codified in 40 CFR §258.61(b), the 30-year PCC period ...
This plan has been prepared in response to direction from the U.S. Department of Energy. The purpose...
Landfills remain the most frequently used method of municipal waste (MSW) disposal. Landfills are de...
This document presents an Environmental Monitoring Plan (EMP) for Waste Area Grouping (WAG 6) at Oak...
This report represents the Geotek Engineering Company, Inc., (Geotek) record of activities to suppor...
The area immediately surrounding a landfill was studied by DC resistivity methods, soil borings, and...
ABSTRACT The Chemical Waste Landfill (CWL) is a 1.9 acre site operated from 1962 until 1985 to dispo...
There is a finite period of time during which the plastic sheeting upper composite liner and lower p...