This research identified significant factors that may influence, or serve as indicators of, potential cost overruns in construction projects. The study used multiple linear regression to analyze data available prior to contract award from 203 construction projects over a full range of project types and scopes. While the proposed model captures 44 % of actual cost overruns, its application reduces average contingency budgeting error from-11.2 % to only-0.3 % for the test sample
This paper presents a quantitative methodology to determine financial impacts of the risk factors du...
Accurate owner budget estimates are critical to the initial decision-to-build process for highway co...
Cost contingency is one component of a project’s budget to cater for cost growth. The determination ...
Cost overruns are a critical problem for construction projects. The common practice for dealing with...
Cost overruns are a critical problem for construction projects. The common practice for dealing with...
© 2014 American Society of Civil Engineers. The determination of a project's cost contingency is a p...
Contingency is a ubiquitous component of project cost estimating. This paper provides a review of th...
The cost performance of building construction projects is a key success criterion for project sponso...
AbstractDue to risks and uncertainties associated with construction projects, owner agencies usually...
A review of the literature supports the inclusion of sufficient contingency to cover risks in constr...
The statistical characteristics of cost overruns experienced from contract award in 276 Australian c...
This research investigates how contingency is currently calculated in project budgets within the bui...
AbstractThis paper focused on examining the effect of various factors on budget overrun in construct...
Winning a bid at a price that yields a profit, is one of the contractor's major goals from bidding. ...
Projects require budgets to set the sponsor’s financial commitment and provide the basis for cost co...
This paper presents a quantitative methodology to determine financial impacts of the risk factors du...
Accurate owner budget estimates are critical to the initial decision-to-build process for highway co...
Cost contingency is one component of a project’s budget to cater for cost growth. The determination ...
Cost overruns are a critical problem for construction projects. The common practice for dealing with...
Cost overruns are a critical problem for construction projects. The common practice for dealing with...
© 2014 American Society of Civil Engineers. The determination of a project's cost contingency is a p...
Contingency is a ubiquitous component of project cost estimating. This paper provides a review of th...
The cost performance of building construction projects is a key success criterion for project sponso...
AbstractDue to risks and uncertainties associated with construction projects, owner agencies usually...
A review of the literature supports the inclusion of sufficient contingency to cover risks in constr...
The statistical characteristics of cost overruns experienced from contract award in 276 Australian c...
This research investigates how contingency is currently calculated in project budgets within the bui...
AbstractThis paper focused on examining the effect of various factors on budget overrun in construct...
Winning a bid at a price that yields a profit, is one of the contractor's major goals from bidding. ...
Projects require budgets to set the sponsor’s financial commitment and provide the basis for cost co...
This paper presents a quantitative methodology to determine financial impacts of the risk factors du...
Accurate owner budget estimates are critical to the initial decision-to-build process for highway co...
Cost contingency is one component of a project’s budget to cater for cost growth. The determination ...