To provide a safe and productive environment, project managers need to plan for the work spaces required by construction activities. Work space planning involves representing various types of spaces required by construction activities in three dimensions and across time. Since a construction schedule consists of hundreds of activities requiring multiple types of spaces, it is practically impossible to expect project managers to specify manually the spatio-temporal data necessary to represent work spaces in four dimension. This paper presents mechanisms that automatically generate project-specific work spaces from a generic work space ontology and a project-specific IFC (Industry Foundation Classes) based 4D production model. The generation ...
Many researchers have studied effective space zoning to reduce the duration of a construction projec...
Extensive research efforts have been made in construction simulation. Nevertheless, work space is ne...
Collaborative AEC technologies centering around component-based CAD models support architectural and...
none2siConstruction production is typically highly dependent upon space to move, store and fabricate...
Workspaces on construction sites represent a key resource due to their limited availability and impa...
This work addresses the problem arising on all construction sites: the occurrence of workspace inter...
With increasing pressure for shorter delivery schedules, space is a critical resource at constructio...
This thesis describes a novel approach for management of work-flow in construction, based on the com...
Schedule float is a fundamental concept in construction planning and control that refers to the flex...
For construction projects implemented in a congested area, the ability to understand spatial relatio...
Traditional design and construction planning tools, such as 2D drawings and network diagrams, do not...
Abstract: The construction space scheduling problem has received relatively little attention from re...
The planning and scheduling of construction projects depends on technological and temporal constrain...
Space availability on a construction site can have a major impact on the efficiency and constructabi...
WorkMovePlan combines the Last Planner methodology, implemented in the WorkPlan software, with space...
Many researchers have studied effective space zoning to reduce the duration of a construction projec...
Extensive research efforts have been made in construction simulation. Nevertheless, work space is ne...
Collaborative AEC technologies centering around component-based CAD models support architectural and...
none2siConstruction production is typically highly dependent upon space to move, store and fabricate...
Workspaces on construction sites represent a key resource due to their limited availability and impa...
This work addresses the problem arising on all construction sites: the occurrence of workspace inter...
With increasing pressure for shorter delivery schedules, space is a critical resource at constructio...
This thesis describes a novel approach for management of work-flow in construction, based on the com...
Schedule float is a fundamental concept in construction planning and control that refers to the flex...
For construction projects implemented in a congested area, the ability to understand spatial relatio...
Traditional design and construction planning tools, such as 2D drawings and network diagrams, do not...
Abstract: The construction space scheduling problem has received relatively little attention from re...
The planning and scheduling of construction projects depends on technological and temporal constrain...
Space availability on a construction site can have a major impact on the efficiency and constructabi...
WorkMovePlan combines the Last Planner methodology, implemented in the WorkPlan software, with space...
Many researchers have studied effective space zoning to reduce the duration of a construction projec...
Extensive research efforts have been made in construction simulation. Nevertheless, work space is ne...
Collaborative AEC technologies centering around component-based CAD models support architectural and...