A feeding buffer is created by starting a project activity before its latest start time to provide adequate protection against project delay. Assuming linear costs for starting activities earlier and a linear project delay penalty, early optimization models for project buffers addressed simple project network structures and invoked the newsvendor model as an approximation. Recently, it had been shown that when the gating activities precede the only stochastic elements in a project, then there exists an exact generalization of the newsvendor model that characterizes the optimal feeding buffers. This insight led to an effective and efficient solution approach by simulation. We show that this result also holds when stochastic elements exist el...
During the last decade a lot of research efforts in the project schedul-ing literature have concentr...
We study projects with activities that have stochastic durations that are modeled using phase-type d...
During the last decade a lot of research efforts in the project scheduling literature have concentra...
In project scheduling or batch supply chain operations, a positive (negative) feeding buffer is crea...
Crashing stochastic activities implies changing their distributions to reduce the mean. This can inv...
This research addresses analyzing and responding to uncertainty in projects with stochastic task dur...
AbstractIn the field of project scheduling, the application of activity floats is often the subject ...
During the last decade, considerable research efforts in the project scheduling literature have conc...
During the last decade a lot of research efforts in the project scheduling literature have concentra...
The project scheduling problem domain is an important research and applications area of engineering ...
Project planning, scheduling, and control are regularly used in business and the service sector of a...
The project scheduling problem domain is an important research and applications area of engineering ...
We investigate project scheduling with stochastic activity durations to maximize the expected net pr...
In many cases, risks that threaten successful project completion can be mitigated (or eliminated) wi...
Solution robust project scheduling is a growing research field aiming at constructing proactive sche...
During the last decade a lot of research efforts in the project schedul-ing literature have concentr...
We study projects with activities that have stochastic durations that are modeled using phase-type d...
During the last decade a lot of research efforts in the project scheduling literature have concentra...
In project scheduling or batch supply chain operations, a positive (negative) feeding buffer is crea...
Crashing stochastic activities implies changing their distributions to reduce the mean. This can inv...
This research addresses analyzing and responding to uncertainty in projects with stochastic task dur...
AbstractIn the field of project scheduling, the application of activity floats is often the subject ...
During the last decade, considerable research efforts in the project scheduling literature have conc...
During the last decade a lot of research efforts in the project scheduling literature have concentra...
The project scheduling problem domain is an important research and applications area of engineering ...
Project planning, scheduling, and control are regularly used in business and the service sector of a...
The project scheduling problem domain is an important research and applications area of engineering ...
We investigate project scheduling with stochastic activity durations to maximize the expected net pr...
In many cases, risks that threaten successful project completion can be mitigated (or eliminated) wi...
Solution robust project scheduling is a growing research field aiming at constructing proactive sche...
During the last decade a lot of research efforts in the project schedul-ing literature have concentr...
We study projects with activities that have stochastic durations that are modeled using phase-type d...
During the last decade a lot of research efforts in the project scheduling literature have concentra...